The project for the construction of improvements to the Conduction Line of the district of San Francisco, specifically the interconnection box No. 1 in Parque Omar, presents a 97% progress is this according to the Comptroller General of the Republic who made a tour to check the progress of the works.

In the inspection carried out by the Comptroller’s Office, it was found that there are pending works such as the installation of pipes at the intersection of Vía Israel towards Boca La Caja, materials that are about to arrive in the country from the United States.
According to the authorities of the National Institute of Aqueducts and Sewers (IDAAN), this work is being built for an amount of $8,764,171.38, positively impacting 75,000 inhabitants of Panama City, the project is financed by the development bank of Latin America.