“The works do not advance“Said the neighbors who live around the Atocha playground, who also assure that for two weeks the machine has been stop and no one is responsible for finish the work.
María Reyes, a neighbor of the place, said that the situation is terrible with all the delays and problems that have arisen since the sinking caused by the clogging of the stream.
In this regard, Klever Padrón, director of Public Works of the Municipality of Ambato, said that the activities will be resumed this Tuesday, November 23, starting at 10:00.
“The stoppage is due to the development of the final designs for the new reinforced concrete collector, a tunnel to pass 15 meters deep below the Rodrigo Pachano avenue”Said Padrón.
In addition, he assured that the replacement from the park and the affected roads around the block will be paved.
The first stage to regenerate will cost approximately $ 300,000 and will last five months. (CNS)