Three days after Unit 1 output of the Holguinera de Felton thermoelectric plant And in the middle of another peak of blackouts on the island, all the East of Cuba It was dark this Sunday night for a “shot” in a transmission line.
The problem occurred in the 220 kV line between Nuevitas and Las Tunas and caused the disconnection of the National Electrical System (SEN) throughout the eastern zone, As reported on their networks the Ministry of Energy and Mines (Minen).
The entity then said that it had begun to work in the restoration, something that was finally achieved at 1:25 in the morning of this Monday, although much of the affected provinces and throughout the country were kept off by generation deficit.
At 1: 25 in this morning the electrical system was restored in the east of #Cuba
– Ministry of Energy and Mines of Cuba (@energiaminascub) SEPTEMBER 8, 2025
Under construction …