The regional councilor for Trujillo Robert de la Cruz Rosas asked the governor of the La Libertad region, César Acuña Peraltaand the representatives of the National Infrastructure Authority (ANIN) to make transparent the real situation in which the definitive works are in the San Ildefonso and San Carlos streams, since the execution modality, Government by Government, prevents any inspection work. by local authorities.
SEE MORE: La Libertad: President Dina Boluarte inaugurates work in El León ravine
What’s more, Robert de la Cruz recalled that the Comptroller’s Office had made observations on the work in the El León ravine, in Huanchaco, but last Thursday afternoon, the President of the Republic, Dina Boluarte Zagarra, arrived in Trujillo to inaugurate the work. , whose purpose is to protect the population from possible landslides and floods during the El Niño phenomenon. She was accompanied by Governor César Acuña.
SEE HERE: They will investigate the purchase of patrol cars in the Regional Government of La Libertad
Report
What the counselor refers to is the control milestone report No. 4219-2024-CG/MPROY-SCC, which points out flaws in the construction of packages C6 and A1, which would affect the quality of the construction site.
It was also alerted that the technical standards of the National Building Regulations, the ACI and the NEC3 Contract signed between ANIN and Besalco Stracon were being breached.
“The report was made public and we expressed our concern, because there were inconsistencies and cracks in several sections of the work. But since we do not have those powers to go and request more information, we do not know how the work has been completed. We are only left with what their media reports. However, it has already been delivered. “I hope that President Dina Boluarte and Mr. César Acuña have verified that the observations were raised, otherwise this would be nonsense,” he emphasized.
READ HERE: Prosecutor’s Office investigates La Libertad Education manager
Uncertain
In this context, the counselor maintained that there is also no clear information on the progress of the works in the San Ildefonso and San Carlos streams. These works, like the El León ravine, are carried out on a Government-to-Government basis.
In this case, it is the United Kingdom government that is in charge of the works and the Besalco Stracon consortium that carries out the work. ANIN supervises.
YOU CAN READ: La Libertad: Businessmen urge the use of technology against the underworld
Advance
The deputy general manager of the Region, Roger Ruiz Díaz, assured that in both the San Carlos and San Ildefonso streams there is progress in the work of 48%. The delay in its execution was due to companies and citizens blocking the land expropriation process.
“ANIN officials have informed us that there is progress of 48%. They are different packages and in the case of the canal that will take the waters to the Moche River, it is 70% complete and what is pending is to end the expropriation of two properties in that area of the river to begin to strengthen the riverside defenses, in order that they can withstand the amount of water that the canal will carry during the rains,” he assured.
The official also reported that the technical file for the storm drainage work for Trujillo has already been completed and in five months the company that will carry out the work should be known.