Despite the unstable weather of the last few days, the main slab load is close to reaching the 4,000 m3 needed to finish. The fact that the Tres Bocas project has its own concrete plant It allows to reach a greater speed in the advances.
For loading the slab, the Tecnoedil company uses two pumps and 12 mixers that extract the product from the plant, located in the same construction area, to load the main slab.
Once the main slab is finished, the other load sections and the works that are part of the tunnel items will be advanced, consisting of: drains, pile screen lining, bottom slab and lighting.
While charging is in progress, the traffic from Acceso Sur avenue is channeled through the collector streets. These arteries are part of the structure of the work and are enabled permanently, speeding up traffic and preventing motorists from passing through the work zone.
It may interest you: Sexual abuse at a school in Asunción: the victim was already the target of bullying
In the intervals in which machinery mobilization is required, trained security personnel notify motorists, following the established protocol, in order to avoid any type of mishap.
Circulation through the collectors is completely signposted with signs and lighting. security officers urge drivers to take precautions and to respect the indications of the banderilleros.