The fourth beam was placed this Wednesday on Bridge 2 de la Barra

The fourth beam was placed this Wednesday on Bridge 2 de la Barra

In this sense, the fourth beam, which was also crawled, rests on the piles that were placed in the bed of the Arroyo Maldonado, as well as beams two and three. Meanwhile, number one is supported on piles that rest on the specially built cofferdams and in record time when the bridge was closed and the situation was verified.

It is worth remembering that on September 23 the engineers detected the breakage and traffic on the bridge was cut off, immediately starting the tasks of primary diagnosis with technicians from the IDM, the MTOP and the collaboration of former Minister Lucio Cáceres, who He was Secretary of State when the bridge was built.

On October 11, more than 200 trucks completed the elaboration of the cofferdams that were the prelude to the piles that served to place the first beam, which occurred on October 19, and thus prop up the bridge. Successively the six piles were placed that served for the placement of the remaining beams. The objective of the administration of the mayor Enrique Antía is that during the month of November the works are finished and to be able to reach the season by enabling it for light traffic.

Source link

Latest Posts

They celebrated "Buenos Aires Coffee Day" with a tour of historic bars - Télam
Cum at clita latine. Tation nominavi quo id. An est possit adipiscing, error tation qualisque vel te.

Categories

When will the 21st century begin in Venezuela?, by Ángel Lombardi Boscán
Previous Story

When will the 21st century begin in Venezuela?, by Ángel Lombardi Boscán

Dominican seasoning in Astros no-hitter
Next Story

Dominican seasoning in Astros no-hitter

Latest from Blog

Go toTop