The Cuban State only completed 42% of the homes planned for 2021

The Cuban State only completed 42% of the homes planned for 2021

The Cuban Ministry of Construction (Micons) only completed 42% of the houses it planned to build in 2021 and 41% of the planned reforms.

According to the ministry’s annual report, collected this Saturday by official media, last year 18,645 homes were completed from the state plans, of the nearly 44,400 planned, and 14,245 were reformed, when the plan pointed to some 34,745.

The Prime Minister of Cuba, Manuel Marrero Cruz, who participated in the presentation of the report, spoke of the “dissatisfaction” of many families due to these breaches, including single mothers with three or more children, according to the Cuban News Agency (ACN). .

Marrero also insisted on giving the “top priority” to the housing program and urged the Micons not to admit justifications and get involved so that the programs are fulfilled.

The Micons plan for this year provides for the construction of 37,991 homes and the rehabilitation of 14,697. The State is the main constructor in Cuba.

The construction sector is experiencing serious difficulties in Cuba, with the lack of supplies such as steel and cement

The construction sector is experiencing serious difficulties in Cuba, with the lack of inputs such as steel and cement being one of the main obstacles.

Last January, it was reported that the housing built by private individuals exceeded what was agreed in the 2021 plan in Sancti Spíritus, while the State fulfilled just over half of what was agreed.

The provincial director of Housing, Néstor Borroto, tells noted in the local newspaper Escambray that the new work was saved thanks to the push of their own efforts and, although it does not give figures of how much expectations are exceeded, the amount seems high.

For February 2021 the plan for the year, added 1,441 new properties to the precarious Sancti Spiritus housing fund. Of these, 993 had to be by private initiative, including 452 basic housing cells (CBH) – about 25 square meters. The remaining 448 would be carried out through state channels.

Borroto now places at 55%, some 246, the state homes delivered and 56% the state CBHs carried out (253 units). “Not so the own effort, which exceeded the agreed figure,” he indicated without saying by how much.

________________________

Collaborate with our work:

The team of 14ymedio is committed to doing serious journalism that reflects the reality of deep Cuba. Thank you for joining us on this long road. We invite you to continue supporting us, but this time becoming a member of our newspaper. Together we can continue transforming journalism in Cuba.



Source link

Latest Posts

They celebrated "Buenos Aires Coffee Day" with a tour of historic bars - Télam
Cum at clita latine. Tation nominavi quo id. An est possit adipiscing, error tation qualisque vel te.

Categories

Fuel prices in Nicaragua will remain frozen this week
Previous Story

Fuel prices in Nicaragua will remain frozen this week

Next Story

Martial law extended in Ukraine for 30 days

Latest from Blog

Go toTop