During the afternoon, the DNCP published that the company Prismapar SA was awarded for a total value of G. 2,537,391,902, and managed to win the tender for the Improvement of the Casilleros Property with the ID 403,057. For this tender, offers began to be received on Tuesday, February 1, 2022.
Municipality of Ciudad del Esté was the institution in charge of carrying out the Call for Tenders No. 403,057 under the category of Construction, Restoration, Reconstruction OR Remodeling and Repair of Real Estateby the type of National Public Bidding procedure.
The aforementioned institution awarded 91 items.
- Preparation and Placement of Work Poster by G. 920.530.
- Demolition of Floors, Ramps and Existing Carpets, Includes Hauling of Debris for G. 40,416,800.
- Pruning, Uprooting and Uprooting of 5 Trees for G. 2,135,250.
- Footings of 0.80X0.80X0.30 Includes Excavation 1.00M Deep for G. 15,184,000.
- Structure of H° A°-Pillars of H° A° by G. 13.950.300.
- Structure of H° A° Lower Beams of 0.15X0.30 Includes Excavation by G. 21,295,560.
- Structure of H° A° Superior Beams of 0.12X0.40 by G. 20.492.706.
- Benches of Hº Aº 1.20X0.60 (According to Eett) by G. 9.565.920.
- Tables of Hº Aº 1.00X0.70 (According to Eett) for G. 5,694,000.
- Garbage dump of Hº Aº (According to Eett) for G. 3,796,000.
- Seedlings of Hº Aº (According to Eett) by G. 5.200.520.
- Asphaltic Horizontal Insulation 3 Sides, With Inorganic Water-Repellent Additive for Wall of 0.15 per G. 1,064,778.
- Elevation Walls of 0.15 to Revoke by G. 28,697,760.
- Plaster of Pillars, Beams, Links and Masonry With Water-repellent by G. 18.365.048.
- Underlayment of Hº de Cascotes (Estimate for Excavation Zones for Underground Ducts) by G. 3,269,305.
- New Regularization File of 2Cm by G. 92.875.783.
- Ceramic Floor Type Pei4 Color White 0.60X0.60 by G. 320.372.910.
- Save Baldozon’s work. Includes Edge Finished by G. 81.186.950.
- Ceramic Floor-Zócalo by G. 5,824,962.
- Metallic Pergola for Access. for G. 41,756,000.
- Provision and Placement of 8Mm Colorless Tempered Glass With Aluminum Structure. by G. 312,505,700.
- 10mm Glass Doors, Includes Metal Handles. by G. 57,609,045.
- Acrylic Latex Coating Based Wall Painting. by G. 37,442,774.
- Painting of Gutters and Downspouts in Synthetic Previous Application of Antirust by G. 9.565.920.
- Exterior and Interior Painting of Metallic Boxes in Synthetic. by G. 159,758,456.
- Painting of Metallic Grills in Synthetic with Antirust Base. by G. 11,900,460.
- Provision and Installation of Pvc Ceiling in a 35Mm Slab Structure Supported on the Structure of the Metal Boxes by means of Profiles by G. 188.041.833.
- Provision and Placement of Canaleta and Caño de Bajada 26 – Development 33 Cms. by G. 26,007,345.
- Channel 0.40M Wide With 1% Slope and Running Grid for Drainage (Includes Excavation, Masonry and Waterproof Plaster) According to Eett. by G. 14,007,240.
- Repair of Sewage Drainage Registry According to Detail by G. 5.029.700.
- Provision and Placement of a Galvanized Sheet Roof No. 26 on a Metallic Structure With Thermal Insulation (Insulation). by G. 84,043,440.
- Provision and Installation of a 630Kva Pedestal Transformer for G. 75,920,000.
- Provision and Dimensioning and Installation of Accessories and Grounding. (Underground Load Breaker, Grounding Conductor, Interior Mufa, 3M Javelins) for G. 30,368,000.
- Provision, Placement and Installation of Measurement Equipment in the Secondary of the Transformer by G. 540.930.
- Provision, Placement and Installation of General Metering Board Ande With Capacitor Bank, According to Norm Ande by G. 18.505.500.
- Provision and Installation of the Main Metal Embedded Distribution Board With Capacity for 12 Keys per G. 341.640.
- Provision and Installation of General Cut-off Key for Main Board of 3X800A by G. 2.873.572.
- Provision and Installation of 4X800A Differential Circuit Breaker for G. 3,985,800.
- Provision and Installation of Power Outlets in Boxes and Corridors by G. 10.659.168.
- Provision and Installation of Schuko Type Sockets for Dining Rooms by G. 6,969,440.
- Provision and Installation of 12W Led Bulbs by G. 5,158,800.
- Provision and Installation of Light Points for Light Bulbs by G. 683.280.
- Provision and Installation of Light Switches in Boxes per G. 495.360.
- Provision and Installation of Led Panels of 36W of 60X60Cm in the Property by G. 25.059.348.
- Provision and Installation of Waterproof Led 36W Ip65 Cold Light by G. 5.252.715.
- Provision and Installation of Exterior Photocell by G. 44.129.
- Provision and Installation of Photocell Support by G. 12.337.
- Provision and Installation of 100W Solar Panels in Garden by G. 19.086.288.
- Provision of 1/2″ Electroduct for G. 2,752,000.
- Provision of 3/4″ Electroduct for G. 9,255,000.
- Provision of 5/8″ Electroduct for G. 4,984,000.
- Provision of Simple Plate for Take by G. 1,488,000.
- Provision of Double Plate for Take by G. 1,860,000.
- Provision of 2Mm Red Color Connectors for Phases for G. 8,732,000.
- Provision of Light Blue 2Mm Connectors for Neutral for G. 5,696,000.
- Provision of 2Mm Green-Yellow Color Connectors for Earth for G. 6,264,000.
- Provision of 4Mm Red Color Connectors for Phases for G. 5,504,000.
- Provision of Light Blue 4Mm Connectors for Neutral for G. 5,788,000.
- Provision of 4Mm Yellow-Green Color Connectors for Earth for G. 6,548,000.
- Provision of 6Mm Red Color Connectors for Phases for G. 19,740,000.
- Provision of Light Blue 6Mm Connectors for Neutral for G. 18,980,000.
- Provision of 6Mm Green-Yellow Color Connectors for Earth for G. 18,600,000.
- Provision of 6mm Color X Connectors for Connection Between Compressors for G. 14,094,000.
- Provision of 6Mm Color Connectors and for Connection Between Compressors for G. 14,376,000.
- Supply and Installation of Metal Embedding Tsp1 With Capacity for 12 Keys per G. 365.365.
- Provision and Installation of Tsp2 Embed Metal With Capacity for 12 Keys by G. 359.671.
- Provision and Installation of Tsp2′ Metal Embedding With Capacity for 12 Keys by G. 367.263.
- Provision and Installation of Tsp3 Metal Embedding With Capacity for 12 Keys per G. 354.926.
- Provision and Installation of Tsp3′ Metal Embedding With Capacity for 12 Keys per G. 360.620.
- Provision and Installation of Tsp4 Metal Embedding With Capacity for 12 Keys per G. 351.130.
- Provision and Installation of Tsp4′ Metal Embedding With Capacity for 12 Keys by G. 363.942.
- Provision and Installation of Tscm Metal Embedding With Capacity for 36 Keys by G. 621.595.
- Provision and Installation of Tscm’ Metal Embedding With Capacity for 36 Keys by G. 647.218.
- Provision and Installation of Tsa Embutir Metallic With Capacity for 60 Keys by G. 749.710.
- Provision and Installation of 1X10A Thermomagnetic Key by G. 1,615,198.
- Provision and Installation of 1X16A Thermomagnetic Key by G. 429.134.
- Provision and Installation of 3X25A Thermomagnetic Key by G. 275.210.
- Provision and Installation of 1X32A Thermomagnetic Key by G. 1,958,736.
- Provision and Installation of 3X40A Thermomagnetic Key by G. 98.696.
- Provision and Installation of 3X100A Thermomagnetic Key by G. 512.460.
- Provision and Installation of 3X500A Thermomagnetic Key by G. 4,517,240.
- Provision and Installation of a 36,000 Btu Cassette Type Air Conditioner for G. 412.245.600.
- Provision and Manufacture of 8X6 Grid Metal Structure for Air Conditioner Compressors for G. 465,000.
- Provision, Connection and Fixation 3/4″ Pvc Pipe for Drainage by G. 18.742.500.
- Provision, Connection and Fixation of 3/4″ Copper Pipe for Refrigerant Gas Coated with Cold Thermal Insulation by G. 59.312.500.
- Supply and Installation of Air Extractor for Each Dining Room. by G. 30,833,010.
- Panel for Extractors, Metal Box to Put On, With General Cut-off Key, Wiring, Copper Bars and Sectional Cut-off Key for Each Dining Room-Cabin. by G. 3,131,700.
- Nyy 2X2Mm Wiring, in Conduit Pipe With Fixing Accessories for Connection of Each Extractor per G. 743.248.
- Copper Pipe 3/4Inch With Fixing Accessories Protection for G. 1.555.400.
- Manufacture of Galvanized Metal Structure Tray for Supporting Air Extractor Pipe by G. 5.353.128.
- General Construction Cleaning Service for G. 2,467,400.
The aforementioned firm’s legal representative is Maria Valbina Vargas de Lugen.
Two more companies responded to the call: Caldetec Engineering Srl and Diego Rodrigo Diaz Mallorquín.
Source: DNCP