He Ministry of Tourism demanded that the builders responsible for the REMOVAL, lightning and repair of the rain drainage of the pier by Samaná, the definitive delivery of the work in a term Not greater than 28 days.
This was reported by the head of the entity, David Colladothrough your account on social network X this Tuesday.
“Therefore, today we have granted a term of 28 days to all builders responsible for the renovation, lighting and repair of rain drainage in the Samaná Maleconto deliver this emblematic work in the agreed timeensuring its enjoyment for the entire community, “said Collado.
The work, which began on August 22, 2022, with a investment superior to those 400 Millions of pesos have been followed by the institution.
The process of Supervisory has the support of Observatory of good practices, made up of the Network of Universities headed by INTEC, representatives of the churches, the tourist cluster and the Hotels Association of Samaná.
“Transparency is a fundamental and not negotiable pillar for us. Thanks to this social monitoring structure We have the legitimacy to demand concrete and timely results, “said the official.
![Samaná Malecón: Tourism requires delivery of the work in 28 days [object HTMLTextAreaElement]](https://resources.diariolibre.com/images/2025/04/23/griselda-5bbef014.jpg)
What are the jobs in it pier from Samaná
The jobs in it pier of Samaná consist of a set of solutions hydraulic In order to mitigate the floods that occur in this area in times of large rains.
This stage lies in the intervention integral to improve runoff of rainwater, from the sanitation of the cane to its mouth in the sea, solid waste retention structure, dredging and repair of tablestacado wall.
It also contemplates the rescue Integral of space urban and leisure of pier Throughout the seafront of the municipality, which covers an area of intervention 1.3 kilometers.
Also includes, Cyclevaybay of Parking On north and south sidewalks, children’s play area, gym and outdoor meditation and circulation spaces.
Also, main entrance square with nine sales modulestwo bath modules, two government offices and two stores.
Four lots
The jobs They are divided into four lots. The first contemplates the improvement of the rain drainage of the pier of Samaná, at a cost of 144,143,579.94 pesos, while the second is the stretch West of the Malecon of Holy Bárbara, for about 140,337,615.39 pesos.
The third is about stretch thisby 83,162,458.82 pesos and the fourth are the works complementary: Welfare and installation of electrical equipment and accessories, at a cost of 38,500,000 pesos, for a total amount of the work of 406,143,654.15 pesos.