Road solution in “Painting” has a total progress of 30%

Road solution in "Painting" has a total progress of 30%

Considered one of the masterpieces of the Government in it Greater Santo Domingothe solution to the avenue’s road junction February 27 with Isabel Aguiar (Painting) It is 30% complete in total and 45% in its western trench, while the goal is to put the work into service in the second half of 2025, reported the Minister of Public works, Deligne Ascencion and the company J.M. that executes the project.

This is a work that will impact more than 300,000 people who come to the place every day from the southern provinces, as well as from the sectors of the northern, southern and eastern parts of the city. Initially, a investment of 80 million dollars from the renegotiation of the contract for 775 million dollars between the state and the company Aeropuertos Dominicanos Siglo XXI (Aerodom).

A great work

Deligne Ascencion indicated that probably the road solution of Paint will be the most work important of the country because it comes to solve one of the most critical points in terms of mobility in it Greater Santo Domingo.

“If I had not had the design of a work like this, we are talking about a year and a half, and be careful if two years, here we had to do a series of studies of traffic of microsimulations to be able to guarantee that the solutions that we are giving contribute to solving the problem,” explained the minister.

Includes the construction of an overpass type trench through Isabel Aguiar Avenue and a tunnel through Gregorio Luperón Avenue, as well as a distributor in the connection with the highway November 6.

The jobs were initiated last April, but although they have advanced to the rite programmedas indicated Flavio Camposfrom the executing company J.M.extra work had to be done than planned due to the emission of the sewer system of the Valdesia Santo Domingo aqueduct, which implied the suspension of the water service. water for a week in sectors of the city.

In addition to this situation, another of the biggest challenges has been to make the interventions affecting the environment as little as possible. transit in the intervened area, which warranted coordination inter-institutional with entities such as the Santo Domingo Aqueduct and Sewer Corporation (Caasd).

According to Campos, all excavation of the western part, that is, from Isabel Aguiar towards Extension 27 are already completed and the drainage also 100% completed.

You may be interested

Solution to Guajimía

He indicated that one of the problems encountered was the downloading of water when it was raining from the intersection towards the Guajimía canyon, but the work included the construction of a lagoon that stores the water so that it does not arrive in large quantities and affect the homes around the canyon, as happened before.

“Here a community was created that grew above this ravine, which impedes the natural flow of the water. The Caasd has an excellent job improving that entire gully to guarantee the flow. However, a solution that we have created together with Public works was to create this lagoon where everyone water that low arrives here earlier and here it is going to have a wait, let’s say, it is going to slow down the water and that eliminates the problem of flood“, he stated.

Response to Leonel

Minister Ascención stated that the best example that the resources coming from the agreement with Aerodom are the works in progress and said that the reviews of former president Leonel Fernández are due to his work of questioning what the Government.

Interviewed during a tour of the jobs of road solution on 27 de Febrero Avenue and Isabel Aguiar, the official said that the progress of this work is carried out with these funds. Ascención stated that with those resources answers are given solutions to the problems that affect citizens in different parts of the country.

Within the projects that are executed with those resources, he also mentioned, the jobs on República de Colombia Avenue, which includes the construction of a north-south tunnel and others that are in the planning phase, such as a bridge where the floating one is and an overpass on Charles de Gaulle Avenue in front of the line station one of the Santo Domingo Cable Car.

“To President Fernández, to whom I give a lot of respect and exquisite treatment as he also does to us, the best example is the progress of this work, which is better than the explanation we can give,” Ascención said.

He maintained that every Thursday he makes a tour of supervision for the works that the Government and, what he did in the intervention of Paint It is not an answer to Fernández’s question.

“Any citizen can raise questions and even more so when that citizen is a important leader of the oppositionthat that is their job to ask questions,” Ascención said.

Graduate in Social Communication from the Dominican University O&M. He has practiced journalism since 1988 on radio, television and newspapers.

Source link

Latest Posts

They celebrated "Buenos Aires Coffee Day" with a tour of historic bars - Télam
Cum at clita latine. Tation nominavi quo id. An est possit adipiscing, error tation qualisque vel te.

Categories

Rio City Hall will take over management of two federal hospitals
Previous Story

Rio City Hall will take over management of two federal hospitals

Look at the results of La Tinka for this Sunday, November 10 (VIDEO)
Next Story

Look at the results of La Tinka for this Wednesday, December 4 (VIDEO)

Latest from Blog

Face to face

Face to face

Embed note December 26, 2024, 4:00 AM December 26, 2024, 4:00 AM Today I read that maturity is understanding that at Christmas the gifts are not under the tree, but rather they
Go toTop