Today: November 24, 2024
August 4, 2024
1 min read

Reasons why the construction of TM along 68th Street in Bogotá will take 2 more years

Reasons why the construction of TM along 68th Street in Bogotá will take 2 more years

The mayor of Bogotá, Carlos Fernando Galán, together with the director of the Urban Development Institute (IDU), Orlando Molano, made a visit to the work on 68th Avenue, one of the most ambitious projects in the capital that is part of the TransMilenio trunk line.

(Further: This is the company that supplies the steel for the construction of the Bogotá Metro).

During the inspection, both officials provided a detailed assessment of the current state of construction, the challenges faced and the progress achieved by the current administration.

For its part, Galán stressed that when he took office on January 1, 2024, he found a project plagued by delays and financing problems.The TransMilenio trunk line along 68th Avenue, with more than 17 kilometers divided into nine sections, should have been much more advanced than it actually was.

Instead of the expected 70% progress, only 38% had been completed. by the beginning of this year.

(Read: Inter-administrative agreement is signed to extend the Bogotá Metro to Soacha).

It is crucial that citizens are well informed about how we receive the works and the steps we are taking to launch them and ensure their completion. This TransMilenio trunk line was contracted in 2020 and was due to be ready in 2025.“, explained Mayor Galán.

However, By August 2024, the work, although it has increased to 51.8% of its progress, still has a long way to go.

(Read: This is how the launching beam works for the Bogotá Metro works).

The mayor and the IDU director said that the project was received with multiple problems, including a lack of coordination between entities, non-harmonized designs and a lack of necessary land. “We have focused on reviewing and correcting all the necessary aspects to speed up the work and make up for lost time.“, added Galan.

Missing resources to continue construction

Regarding resources, Galán revealed that, during the handover, the previous administration mentioned a shortage of between 500 and 600 billion pesos for the IDU contracted works.

However, a detailed review revealed a real deficit of close to two billion pesos to finish the works already contracted, including 434 billion needed to finish the one on 68th Avenue.

(Further: ‘The discovery does not affect the development of the works’: IDU on the Comptroller’s report).

We have dedicated ourselves to securing the necessary resources through efficient management and by working closely with auditors and contractors. Thanks to this, we have made significant progress in the District Development Plan to ensure the completion of these critical works for Bogotá.“, Galán concluded.

BRIEFCASE



Source link

Latest Posts

They celebrated "Buenos Aires Coffee Day" with a tour of historic bars - Télam
Cum at clita latine. Tation nominavi quo id. An est possit adipiscing, error tation qualisque vel te.

Categories

Previous Story

Gustavo Leal F.: The clinic is ours and its health committees

Bolivia, facing the urgency of a fiscal adjustment
Next Story

There is an opportunity to hear the voice of the people

Latest from Blog

Go toTop