Piura: Comptroller alert deterioration on the site of the Los Algarrobos Health Center

Piura: Comptroller alert deterioration on the site of the Los Algarrobos Health Center

The Comptroller detected that the work of improvement of the services of the Health Center Los Algarrobos de Piura, valued at more than S/60 million and that is paralyzed, is exposed to which would affect your reactivation. He also indicated that the Regional Government of Piura does not have the budgetary resources that guarantee the execution of the work balance.

Control report No. 10077-2025-CG/GRPI-SCP details the status of the work. Through Charter No. 18-2024-ARQ.CONST360-ALGARROBOS, they presented the final report of the technical file of the work balance of the project that has an approximate cost of S/ 61´224, 803.66 and with Office No. 351-2025/ GRP-440330 of 03-04-2025, the Directorate of Studies and Projects gave conformity.

However, the Regional Piura Control Management with Office No. 0670-2025-CG/GRPI of 01-07-2025, notified Report No. 5477-2025-CG/GRPI-SCC corresponding to the control milestone No. 14, with the purpose that the GORE, adopts corrective or preventive actions regarding the facts identified.

You can see: Piura: They dictate preventive detention to subject for theft of woman

“It is noted that the technical file of the work balance is not approved and the paralyzed public works is exposed to risks of deterioration of the infrastructure executed, so that the adoption of immediate actions for reactivation is required, in order to prevent the loss of public resources, deterioration and consequently to make available the provision of public services for the benefit of the population,” says the Comptroller’s report.

They detail that the technical file of the work balance projected variations to the equipment components, reverse osmosis system and emergency system with the generator group without due technical support, compromising its reliability and generating risks in the quality, opportunity and cost of the work.

The report details that, when making a comparison, between the medical equipment considered in the primal technical file and the equipment included in the work balance file, a decrease and elimination of 34 types of medical equipment is noticed.

Likewise, the Comptroller said that Gore Piura has not arranged resources that guarantee the execution of the work balance; Despite financing requests from the competent authority, which could cause delays in the process of reactivation of the work.

“(…) of the consultation made to monitor the budget execution (friendly consultation) of the web portal of the Ministry of Economy and Finance as of August 2025, it is appreciated that the aforementioned project does not have an institutional opening budget (PIA) for fiscal year 2025, subsequently contributing to the modified institutional budget (PIM) of S/ 389,365.00,” says the Report of the Comptroller of the Republic.

Source link

Latest Posts

They celebrated "Buenos Aires Coffee Day" with a tour of historic bars - Télam
Cum at clita latine. Tation nominavi quo id. An est possit adipiscing, error tation qualisque vel te.

Categories

Francisco Javier García: "The PRM inaugurates incomplete works and deceives the people"
Previous Story

Francisco Javier García: “The PRM inaugurates incomplete works and deceives the people”

Next Story

SSPC and Telefónica execute pilot plan against extortion

Latest from Blog

Go toTop