The MOPC detailed that the Effluent Treatment Plant for said headquarters reached 29.62% execution.
In turn, he indicated that other areas such as the structural interconnection gallery, the visitor sector ramp and the lower and upper water tank reached 100% progress.
Meanwhile, the dining area plus the sports sector, the ground floor for visits and workshops, as well as the administration on the top floor and the security checkpoint, are also in the final phase.
This new penitentiary headquarters consists of 8 modules, one of which is high security. All of them are designed to comply with rehabilitation, training and social reintegration, a program to be implemented by the Ministry of Justice.
This is one of the two penitentiaries being built in the city of Emboscada. Together with that of Minga Guazú, department of Alto Paraná, they will have the capacity to house a total of 3,960 people deprived of their liberty.