The Bella Vista Wastewater Treatment Plant (PTAR) in Asunción will start operating to join the other two, already in operation, in Varadero and San Lorenzo, the latter in the department of Central.
With a 95% progress, the work schedule contemplates, these days, the assembly and installation of mechanical and electrical equipments in the second WWTP that the capital will have.
His Construction is part of the Asunción Bay and Metropolitan Area Sanitation Programpromoted by the MOPC.
Read: They obtain images of the attack: hitmen shot without getting out of the car
Some of the tasks in progress are the installation of the medium voltage overhead line and electrical appliances of the booths for the boards and buildings, in addition to the wiring of the boards of the electrical substation building.
The finishing works and adjustments of the buildings and some concrete works of one of the pumping stations are also continuing.
interlocks to banks of the Mburicaó stream, in the area of Bañado Norte, this work occupies an area of 8,100 square meters, of the 10,000 that the land where it is located has.
It will be able to process a flow of 4,400 liters of wastewater per second.
Treatment will consist of removal of all trash, solid waste and sand, present in the liquids evacuated through the sanitary sewer system.
Read More: Operation Silvestre: two tentacles of organized crime fall
In this way, it will reduce the polluting load dumped today into the Paraguay Riverthrough existing direct downloads.
The result will be an improvement in the quality of the waters and their ecosystem, the environment of the channel and the quality of life of the population of Asunción and the metropolitan area.
You will also have a laboratory designed to monitor wastewater entering the Plant, discharged effluents and the water quality of the Paraguay River.