Groundbreaking for improvement work on Avenida Eusebio Ayala and Bruno Guggiari

The start date of the work is set for September 28. Yesterday, together with the initial shovel, the order to start works was delivered to the construction company with the already announced term of 180 days.

The contractor company is: Tecnología del Sur SA The contractual amount is 8,999,419,477. Deadline established for delivery of the work: 180 calendar days, excluding the mobilization period (10 days)

Sections to intervene with their main items to execute:

Av. Eusebio Ayala in 2 sections – Between Choferes del Chaco and Cedro Between Avda. Guido Boggiani and Madame Lynch.

Pavement milling in poor condition. Potholes. Hydraulic concrete gutters and speed bumps. Demolition and construction of hydraulic concrete folder. Regularization with hot asphalt concrete. Hot asphalt concrete folder. Removal and replacement of laces. Repair of central separator.

Av. Bruno Guggiari e/ Av. Eusebio Ayala and Ecuador Milling of asphalt pavement. Potholes. Hydraulic concrete gutter. Speed ​​bump and hydraulic concrete folder. Regularization with hot asphalt concrete. Hot asphalt concrete folder. Readjustment of running water network. 0Horizontal signaling with thermoplastic paint -Concrete cordons to improve the central separator.

The entrance Groundbreaking for improvement work on Avenida Eusebio Ayala and Bruno Guggiari was first published in diary TODAY.

Source link

Previous Story

What vehicles and brands are the favorites of Peruvians?

Next Story

Pre-exposure pill against HIV is available in Panama

Latest from Paraguay