CC señala supuesta “falta de planificación de obras” en Plan de Humanización de Jean Alain

CC points out alleged “lack of planning of works” in Jean Alain’s Humanization Plan

An audit report submitted by the Chamber of Accountspoints out alleged faults in the “planning of works” that were carried out in the management of the former prosecutor Jean Alain Rodríguez in the Plan of Humanization of the Penitentiary System of the Dominican Republic.

The “lack of planning of the works” in this flat would have cost him in final contracts around of RD$8,535,985,106 to the State from the Attorney General’s Office (PGR).

Likewise, it includes “hidden defects in the construction of work, amounting to an amount of RD$438,715,007”.

You can read: Luis Carvajal says “lack of management” prevails in the Ministry of the Environment

same way, they were allegedly disbursed RD$529,957,818 “without invoices or supporting documents of the expense”.

Other “irregularities” committed were the “absence of inventory reports and records in the fixed assets, amount to the sum of RD$1,522,035,660”; “weaknesses and vulnerabilities found during the physical inspection, for the amount of RD$348,299,904”.

This report of the Chamber of Accounts It is carried out at the request of the Specialized Attorney for the Persecution of Administrative Corruption (PEPCA) during the period August 16, 2016 to August 16, 2020.

It is recalled that the former attorney Jean-Alain Rodriguezis in preventive detention in Najayo Hombres for his designation as the main accused of an alleged network of administrative corruption revealed in the controversial Medusa case.

Source link

Previous Story

The corrective payment suggested by the government: which sectors accepted and which did not

Next Story

Technological solutions market grows among Peruvian companies

Latest from Dominican Republic