This Saturday, January 18, Mayor Carlos Fernando Galán shared a video in which he showed the installation of the first rails of what will be the Bogotá metro.
Galán indicated that these belong to the Metro line 1that is, this first section will be the test line that It will be 905 meters long in the Patio Taller and which, after that, will connect with the garages, with the metal bridge and with the viaduct.
“This year the first train arrives in September and it is on this line where it will do the first tests, as it has the capacity to move trains at a speed of up to 80 kilometers per hour. We are installing sleepers and rails“said the president.
(See more: ‘Flirt’ by the Petro government to the District to postpone some of the Metro payments)
According to Leónidas Narváez, manager of the Metro company, Chinese operators will be in charge of directing the test in question. There will be 120 kilometers of rails that will go on the sleepers, which arrived from China to the countryseveral months ago.
Likewise, the district president indicated that the metro works were received at 28.98% and as of December 31 it was at 46.24%; That is to say, they have had an advance of 17.26% in this year of the Galán administration. “Today there are more than 1700 meters of viaduct built”.
The same way, It is estimated that by the end of 2025 the works will be more than 67% complete.as well as the arrival of the first train from China.