The Comptroller General’s Office identified that officials and former officials of the Regional Government of Junín modified requirements of the selection process to benefit a consortium without the necessary experience in hospital works, compromising the execution of the Manuel Higa Arakaki Hospital project, valued at more than S/ 207 million.
LOOK AT THIS: They warn that household drains flow into canalization work in Chilca
According to Specific Control Report No. 17604-2025-CG/GRJU-SCE, the selection committee reduced technical requirements, accepted unsupported observations and awarded the contract to a consortium whose main member would assume 97% of the contract without proving the required specialty. Despite not meeting all the requirements, including the occupational health and safety specialist, the contract was signed in violation of principles of equality and competition.
YOU MAY BE INTERESTED: Santo Domingo de Acobamba: Population walks from 7 hours to 3 days to reach their destinations
The control entity concluded that these actions affected the transparency of public procurement and limited the participation of suitable bidders, compromising a key work for the attention of thousands of citizens of Satipo. Although the GORE Junín later annulled the contract, the Comptroller’s Office identified alleged criminal and administrative responsibility in five officials and referred the case to the Anti-Corruption Prosecutor’s Office to initiate legal action.