The trains that the mayor of Lima, Rafael López Aliagabrought from USA As part of a “donation” for the route Lima-Chosicathey would be launched within 39 months, according to the Deputy Minister of Ministry of Transportation and Communications (MTC), Ismael Sutta. After the second dialogue table that no representative of the MML attended, Sutta said that it will be sought to reduce the times so that the locomotive and cars can work.
“We consider that the issue of contractual modification and the incorporation of state resources for the improvement of infrastructure, to make it safer, currently corresponds to the concessionaire, the MTC, MEF, Ositran, that we have to work quickly. Initially, according to the proposal presented under the scheme that the MTC handles with reference to the elaboration, times, technical files, technical files, We had determined that they were 39 months considering the property issuehe commented.
You can see: Pedro Castillo stars in tense exchange of words with judges: “I am a kidnapped president, this trial is political”
Along the same lines, Sutta stressed that part of the delay is due to the fact that they will take security measures so that the homes that are close to the roads are not at danger.
“Part of the section of the road, the neighborhood units, the houses are very close to the railway infrastructure and that, in turn, if we do not take any consideration, especially for the crosses, we could have security problems. Now, what we are agreeing is that we are going to work among all the authorities to make more famous that time and that will come out depending on the consensus with all the actors that are determined,” he said.
“If we reduce time in the property issue, we could reduce times. Initially, those 39 months, I do not want to give a date on which we can reduce, but yes, based on meetings, we will make this time in the least possible,” he said.
It is important to mention that today’s work meeting, the representatives of the Ministry of Economy and Finance (MEF), Sunat, Ombudsman, Ositran, ATUNGO Luz Ambar and the Andina Central Ferrovías concessionaire.
You can see: When is the election of the new Board of Directors of the Congress?: 2 Lista struggles the presidency
The Municipality of Lima did not attend the meeting, after the mayor López Aliaga announced yesterday, that they would not be part of the working group and criticized the minister César Sandoval for its management with trains Caltrain.
Authorities regret absence of the MML at work table
On the other hand, the president of Ositran, Veronica Zambrano, regretted that the Municipality of Lima has not attended the work table for the implementation of trains for the Lima-Chosic route. Zambrano stressed that the municipality assistance was important to listen to their proposals and work with all the actors.
“We are gathered because that was the commitment we had of the last meeting. Yes, we regret the absence of the Municipality of Lima, because although it is true, we can separate, according to the last proposal I have heard from the MML, which is the choice of the operator of what are going to be the modifications of railroad. Wanting to know the characteristics of the railroad where you will have to put your rolling material, “he said.
On the other hand, the head of Ositran urged the Municipality of Lima to return to the work table in order to adjust the deadlines for the operation of the trains and recalled that the MML had given its word at the first work table.
“We hope that the MML will again join this team to be able to advance. The deadlines as the vice minister has indicated are referential and, within the table having all the institutions, it can be adjusted that this is the idea. We have talked about other possibilities in the development of the project, such as the Fast Track, which is used in other projects and that is allowed by law. For that we need to be all the actors. As I said at the last meeting and we had his word, “he said.