Emir Olivares and Arturo Sánchez
La Jornada newspaper
Thursday, February 20, 2025, p. 11
The branch that will connect the train of the Interoceanic corridor of the Isthmus of Tehuantepec (CIIT) with the two mouth refinery will be ready the last quarter of 2026, said the project director, Vice Admiral Juan Carlos Vera Minjares. It is that, he said, there are only 39 percent of the right of track.
During the morning of President Claudia Sheinbaum Pardo, the Naval Command presented the advances of the ambitious multimodal system that will link the Pacific and Atlantic oceans and promotes the economic development of the region.
Its land influence area is made up of four states: Veracruz, Oaxaca, Tabasco and Chiapas, 105 municipalities and more than 4 million 600 thousand inhabitants
.
He explained that 61 percent of the right of track for the line that will lead to the Olmeca refinery, which goes from Huiman-Guillo to two mouths, has not yet been released, for which it works hand in hand between the Secretariats of the Navy (in charge of the CIIT) and that of agricultural, territorial and urban development, together with the Government of Tabasco.
We calculate in six months to have the total release to, as of May, to start work; We have an estimated construction time of 18 months and its term is scheduled for the last quarter of 2026
he pointed out.
He recalled that the CIIT train consists of three lines: the Z of 307 kilometers of track and joins the ports of Salina Cruz, Oaxaca, with that of Coatzacoalcos, Veracruz. Operations began on December 22, 2023, the date has already transported more than 63 thousand passengers and 316 thousand tons of load.
The FA, of 310 kilometers, goes from Coatzacoalcos to Palenque, Chiapas, to connect the CIIT with the Mayan train. 100 percent operational has been located since September 13 of last year and has transported more than 19 thousand passengers and 29 thousand tons of cargo
.
And line K, which will link Ixtepec, Oaxaca, with Ciudad Hidalgo, Chiapas, on border limits with Guatemala, for which 459 kilometers of roads and 14 stations are being rehabilitated. It is estimated to conclude the work in the second quarter of 2026.
Vera Minjares said that the corridor will have 13 development poles for well -being: four in Veracruz, six in Oaxaca, one in Tabasco and two in Chiapas.
Of these, the concession was already granted to eight, through international public tender: three to the multimodal developer of the Isthmus for vehicle and auto parts distribution projects; Four to Proistmus and Profharmax firms, for the development of agribusiness, medical and metal devices, and one to the Marzal company, dedicated to high quality aluminum recycling.
The Vice Admiral said that the maritime-port area of the CIIT is comprised of four ports: Coatzacoalcos, Salina Cruz, Dos Bocas and Puerto Chiapas.
He announced that a pilot test will be carried out soon for an interoceanic car cross through the services offered by the multimodal logistics platform.
President Sheinbaum Pardo said The interoceanic train is going very well. In the first quarter of 2026 it will operate 100 percent
.