The Atalaya-Mariato and Calidonia Highway to Pixvae in the Soná district, Veraguas province is already 50% complete, as revealed by the Minister of Public Works, Rafael Sabonge, who assured that this project could be completed in 2023 .
This Wednesday, October 19, during a tour in the province of Veraguas, in which the Mariato-Quebró highway was inspected, Sabonge assured that this project is already 87% complete and “we are seeing some places, some critical points to be This is a flood zone.
He added that the Soná-Calidonia-Pixbae highway will have 44 kilometers of new road, since the existing ones are in very poor condition. I emphasize that they are in the process of paving and have placed about 6,000 tons of asphalt in this project that is opening up not only production but also tourism.
«We were there talking with the local authority, with the producers, the residents; visiting a school that unfortunately suffered from the floods and they told us that these rains that occurred 2 weeks ago had not happened in almost 60 years », he said.