The works of the future basic hospital of Yataity del Norte, San Pedro, were interrupted due to protests by one of the bidders, which was accepted by the National Directorate of Public Procurement, for which the progress of the works is at a standstill. by, as long as the impasse is resolved.
In this regard, the health portfolio mentioned that at the request of the General Directorate for the Development of Health Services and Networks – on May 6, 2021 – began the process of designing the Future Basic Hospital Project for the Yataity del Norte district, thus raising the category of the current Family Health Unit.
On May 7 last, the Physical Resources Directorate – dependent on the DGAF/MSPYBS – carried out the project delivery prepared for consideration and steps to obtain financing.
Read: Cleaning staff electrocuted to death
Through Resolution SG No. 1053 “by which the call is authorized, the specifications and conditions are approved and the bid evaluation committee of the call for national public tender No. 117/2021 “construction project of the basic hospital of Yataity del Norte – Ad Referendum – ID No. 404,947 “dated December 7, 2021, the relevant administrative procedures are initiated for the corresponding call for the Construction of the aforementioned health facility, once the financing has been obtained through the Budget General Expenses of the MSPYBS and the pertinent permits (Municipal Approval and Environmental License of MADES)
Opening of offers (Call 1): April 12, 2022
Declaration void by DGAF Resolution No. 828 dated May 25, due to the fact that the offers submitted are unacceptable due to their substantial variation with respect to the estimate made.
Update of reference prices: Delivered by the Directorate of Physical Resources on May 30, 2022
A new call process is initiated from the declaration of desert of the previous one, using Resolution SG No. 1053/21.
Also read: artificial intelligence vs. the recurring desire to steal from the Paraguayan State
Opening of offers (Call 2): July 20, 2022
Signing of the contract with Ing. Julio Galiano Morán (awarded): August 02, 2022 due to the rush to start the works.
Start of work: August 5, 2022
Protest to the award presented to the National Directorate of Public Procurement by the firm Caraguatay SA – DNCP Resolution No. 2,748/22 dated August 9, 2022.
Note from the company of Ing. Julio Galiano Morán on the urgent measure or contractual prudence of work suspension dated September 16, 2022.
To date, the Evaluation Committee is carrying out the process of re-evaluation of offers, estimating the following processes and deadlines to be considered from the conclusion of the analysis: