This Sunday, the service on Line 1 of the Caracas Metro system was normalized, after the work in the maneuvering zone that was being carried out at the Agua Salud station.
For these works, it was necessary to enable a temporary single track between Propatria and La Hoyada stations.
«The Temporary Single Way is lifted (#VUT) between stations #homeland Y #LaHoyada. The passage of trains on both tracks is normalized #Line1 after completing the work in the maneuvering area of #WaterHealth carried out under the plan #ElMetroSeMoeveContigo“, wrote the Caracas Metro System in its account on the social network Twitter.
Among the works carried out at the Agua Salud station, is “the replacement of 2 cores, the performance of three aluminothermic welds, one eclipse, geometric control of the line and crossing of the area.”
These works are part of the plan The Metro Moves With You.
For the full recovery of this Transport systemthe Venezuelan head of state approved 150 million dollars and 16 million euros for rail investment.